PMP Question 135

Home Forums PMP Questions and Answers Discussion PMP Question 135

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #7605
    admin
    Keymaster

    Team is working on the project ABC. It encountered problem in an activity with the free float. Due to this, its duration got extended by the project manager. What is MOST likely to be affected in this situation?

    a. Resource schedules
    b. Project duration
    c. Start date of the successor activity
    d. Scope management plan

    #7606
    admin
    Keymaster

    Correct answer is A.

    Since an activity with float will not affect the project duration as long as any delay is not greater than the float, choice B could not be best. Choice D cannot be best as this situation is not related to scope, just time. An activity with free float means it has time where it can be delayed without impacting the next activity. Therefore, choice C cannot be best. Any delay in when an activity is to be completed will most likely impact resources schedules.

    Pass PMP in the First Attempt : PMP Strategy

    PMI 200 PMP questions Solution : PMI-PMP Practice Exam

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.