Project manager was setting up the agenda for the next project meeting. Few members argued over one feature. Some said it should be included for detailed discussion while others said it would be too early to go for detailed discussion. Project manager decided to include it but mentioned that only high level discussion would be done for this feature. Which conflict resolution technique is being used by project manager?
a. Smoothing
b. Withdrawal
c. Compromising
d. Forcing