PMP Question 132 Home › Forums › PMP Questions and Answers Discussion › PMP Question 132 This topic has 1 reply, 1 voice, and was last updated 5 years, 8 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts August 6, 2020 at 5:24 AM #7561 adminKeymaster Generally on an Agile project, who can provide the best estimation of the tasks? a. Development Team b. Product Owner c. Scrum Master d. Subject Matter Expert August 6, 2020 at 5:26 AM #7562 adminKeymaster Correct answer is A. Since Development Team executes tasks so they are the closest to the technical details of the project. They can best provide the estimation regarding size and time required to complete the tasks. Pass PMP in the First Attempt : PMP Strategy All PMP Question & Answers: Question & Answers Revise PMP Concepts: PMP Concepts PMP Tips & Tricks: PMP Tips & Tricks PMP Knowledge Area based Quiz: 20 Questions Challenge 50 Questions Challenge PMP Agile based Quiz: 20 Questions Challenge 50 Questions Challenge Study Groups: Whatsapp Telegram Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Please enter an answer in digits:four × four = Log In