Correct answer is D.
Cycle Time = WIP / Throughput. Throughput can be increased by increasing WIP or decreasing Cycle Time or adding more members to the team so that more work can be done in the given period of time. Size of user stories doesn’t matter as team will be able to complete story points corresponding to their velocity in the sprint.