The correct answer is D.
Answer D is correct. You know you are under budget since the CPI is greater than one, but you don’t know by how much. You also do not know how you are doing on schedule. To find out, first calculate the EV from the data presented; EV = CPI x AC = 1.1 x $800M = $880M. Now you can determine the CV, SV, and the SPI. CV = $880M – $800M = $80M; SV = $880M – $890M = -$10M; SPI = $880M / $890M = 0.99. Based on this information you are about on schedule and $80M under budget. Answer A is incorrect. You are behind schedule by $10M worth of work, or 1 percent of the total. Answer B is incorrect because you ARE behind schedule by a little, not ahead. Answer C is wrong since that team activity would have already been planned into the budget. We don’t use excess unless specific risk events occur which were planned for and approved in the plan.
Pass PMP in the First Attempt : PMP Strategy
Revise Cost Management Concepts: Project Cost Management
Quiz:
20 Questions Challenge
50 Questions Challenge