Correct answer is B.
Option A is incorrect because helping the organization to adopt Agile is one of the Scrum Master responsibilities.
Option C is wrong; meeting individually with each team member is not a problem but focusing only on the Scrum Master may not be the right approach.
Option D is incorrect as Sponsor asks for the help but does not ask to move to a new team permanently.