  • #11749
    admin
    Keymaster

    An experienced agile practitioner has been assigned to work on two different projects at a time. In a day, on a rough approximation, he is spending 50% of his time on each of the projects. Which of the following is the type of waste that will most likely occur in such an arrangement?

    A. Defects
    B. Task switching
    C. Partially done work
    D. Motion

    #11750
    admin
    Keymaster

    Correct answer is B.

    Agile Practitioner is switching tasks in between two projects. This is “Task Switching” waste mentioned in seven wastes in lean management.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.