    An agile team was performing very well till the fourth iteration. However, due to some unforseen situations, it was not able to complete any storiy in the fifth iteration. How this situation will effect the burndown chart?

    a. Slope of the burdown chart will become negative
    b. Slope of the burdown chart will become zero
    c. Slope of the burdown chart will become positive
    d. Since the situation was unforseen so fifth iteration would be cancelled

    #11605
    admin
    Keymaster

    Correct answer is B.

    Since zero story points are completed so the burdown graph would become flat. Thus slope would become zero.

    Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : Youtube Channel

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.