    An agile team has successfully completed the retrospective process. The facilitator wants to know how the session went. Which of the following technique can help him to gather feedback about retrospective process?

    a. ROTI
    b. ROI
    c. Plus/Delta
    d. SMART goals

    #11588
    admin
    Keymaster

    Correct answer is A.

    ROTI stands for Return on Time Invested. It is used during the closing phase of the retrospective process to know about the effectiveness of the retrospective session.

    Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : Youtube Channel

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.