    Organization ABC has been following Agile to execute their projects. Recently they started the complex project and the team wants to know the high level requirements so that they can start the work. How would you proceed?

    a. Refer the Project Roadmap
    b. Refer the Project Charter
    c. Refer the Product Backlog
    d. Refer WBS

    #11572
    admin
    Keymaster

    Correct answer is A.

    Product Roadmap contains high level plan which depicts what all user stories will be implemented in which release.

    Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : Youtube Channel

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.