Agile Question 270

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11196
    admin
    Keymaster

    Team ABC adopted Agile to execute the project. Velocity for the first sprint was 18, second sprint was 12, third sprint was 20, fourth sprint was 22, fifth sprint was 22, sixth sprint was 24. What indication it might give on the team formation stages after sprint 6?

    a. The team is in the formation stage
    b. The team is in the storming stage
    c. The team is in the norming stage
    d. The team is in the performing stage

    #11197
    admin
    Keymaster

    Correct answer is D.

    Since the velocity has increased from initial sprints and is now stable, therefore, the team has moved from the storming stage to the performing stage.

    Tips/Tricks/Cheat sheet to master PMI-ACP Exam and Concepts : PMI-ACP Tricks/Tips/Cheat sheet

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.