Agile Question 247

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #11072
    admin
    Keymaster

    During the first iteration, the team estimated to complete 5 user stories. Development part of each user story is estimated at 3 story points and testing part is estimated at 2 story points. By the end of the iteration, team developed and tested 4 user stories and developed the fifth user story but could not test it. What was your team’s velocity for the first iteration?

    a. 15
    b. 20
    c. 23
    d. 25

    #11073
    admin
    Keymaster

    Correct answer is B.

    In Agile, velocity is calculated on basis of completed user stories. Impartial work doesn’t contribute towards the velocity.

    Learn PM concepts through daily life experiences : Video Tutorials

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.