Agile Question 198

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #10738
    admin
    Keymaster

    An agile team was performing very well till the fourth iteration. However, due to some unforeseen situations, it was not able to complete any story in the fifth iteration. How this situation will effect the burndown chart?

    a. Slope of the burndown chart will become negative
    b. Slope of the burndown chart will become zero
    c. Slope of the burndown chart will become positive
    d. Since the situation was unforeseen so fifth iteration would be cancelled

    #10739
    admin
    Keymaster

    Correct answer is B.

    Since zero story points are completed so the burndown graph would become flat. Thus slope would become zero.

    Video Tutorials : Video Tutorials

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.