    Which of the following statements is true?

    a. In Agile, Risk is low at the beginning and then increases and after sometimes it decreases.
    b. In Agile, Risk is high at the beginning and then decreases rapidly.
    c. In Agile, Risk is high at the beginning and then decreases and after sometimes it increases.
    d. In Agile, Risk remains low throughout the project

    #10657
    admin
    Keymaster

    Correct answer is B.

    In Agile, high risk items are placed at the top of the product backlog which ensures they are developed at the earlier stage. This helps in decreasing risk rapidly as the project progresses.

    Project Management Case Study : PM Case Study

    Video Tutorials : Video Tutorials

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.