Correct answer is B.
Scrum Team should be fully dedicated to the project on which they are working upon. Since Project switching is kind of waste and if Sameera is getting work for previous project too so chances are there that the current project may suffer, if not now then may be in the future. Daniel, being the scrum master, should protect his team from the distractions and discuss the situation with Sameera’s manager that let her fully dedicated to the Project ABC only.
Video Tutorials : Video Tutorials
Agile Resources : Agile Resources
World of Project Management : Mobile App
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram