    Product owner along with agile team is priortising the work items. Considering all other factors same, which of the following items will be developed first?

    a. Business benefit $3000 and cost of development $1500
    b. Business benefit $3000 and cost of development $1000
    c. Business benefit $5000 and cost of development $4000
    d. Business benefit $5000 and cost of development $6000

    #10483
    admin
    Keymaster

    Correct answer is B.

    In Agile, higher business value item is developed first. Value based analysis helps in deciding true business value after factoring in development cost. In the question, option B has the business value of $3000 – $1000 = $2000, which is highest among all the options.

    Video Tutorials : Video Tutorials

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.