    An Agile team is using burn-up chart to measure its progress. After plotting the burn-up chart, team found that it is steadily increasing. What does it indicates?

    a. No. of story points being completed in every iteration is increasing
    b. No. of story points being completed in every iteration is decreasing
    c. No. of story points being completed in every iteration is constant
    d. No. of story points being completed in every iteration is zero

    #10335
    admin
    Keymaster

    Correct answer is C.

    Since the burn-up chart is steadily increasing, therefore, the slope i.e. velocity is same. As velocity represents the number of story points completed per iteration, therefore, number of story points completed per iteration is constant.

    Agile Resources : Agile Resources

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.