Home › Forums › PMP Questions and Answers Discussion › Stakeholder Management Question 8 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 4, 2019 at 5:26 AM #2288 adminKeymaster After obstacles to process have been successfully removed, what should be the level of engagement of the stakeholders? A. Leading B. Neutral C. Supportive D. Resistant October 4, 2019 at 5:28 AM #2289 adminKeymaster Correct answer is C. Pass PMP in the First Attempt : PMP Strategy Revise PMP Concepts: PMP Concepts Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In