    During stakeholder identification, it important to consider organizational process assets, what would not be provided by organizational process assets during this process?

    A. Government or industry standards
    B. Stakeholder register templates
    C. Lessons learned
    D. Stakeholder register from previous projects

    #2226
    admin
    Keymaster

    Government or industry standards are part of enterprise environmental factors, not organizational process assets.