    The ability of the project manager to correctly identify and manage the stakeholders and manage them in an appropriate manner can mean the difference between success and failure. Which of the following statements about stakeholders in not correct?

    A. The project team should identify internal and external, positive and negative, and performing
    and advising stakeholders in order to determine the project requirements and expectations of all
    parties involved.
    B. Stakeholders have varying levels of responsibility and authority when participating on a projectand this level cannot change over the course of the project’s life cycle.
    C. The stakeholder involvement may range from occasional contributions in surveys and focus groups to full project sponsorship which includes providing financial, political, or other support.
    D. Stakeholder identification is a continuous process throughout the entire project life cycle

    #2202
    admin
    Keymaster

    Correct answer is B.

    Stakeholders have varying levels of responsibility and authority when participating on the project. This level can change over the course of the project’s life cycle.

    Revise Stakeholder Management Concepts: Project Stakeholder Management