    During Identify Stakeholders process, we identify all potential stakeholders and relevant information, such as their roles, departments, interests, knowledge, expectations, and influence levels. All the following statements are correct EXCEPT:

    A. Key stakeholders are easy to identify.
    B. Other stakeholders cannot be identified by interviewing identified stakeholders.
    C. Project manager needs to expand the list of identified stakeholders until all potential stakeholders are included.
    D. Key stakeholders are those who have a decision-making or management role in the project.

    #3344
    admin
    Keymaster

    Correct answer is B.

    Key stakeholders are usually easy to identify as the list of key stakeholders is provided in the project charter. Key stakeholders include anyone in a decision-making role or management role, such as Sponsor, Project Manager, and Primary Customer! Identifying other stakeholders is usually done by interviewing identified stakeholders and expanding the list until all stakeholders are included!

    Pass PMP in the First Attempt : PMP Strategy

    Revise Stakeholder Management Concepts: Project Stakeholder Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.