    What is NOT common between stakeholder management plan and communications management plan?

    A. Both contain stakeholder communication requirements
    B. Both contain information to be distributed, including language, format, content, and level of
    detail.
    C. Both contain timeframe and frequency of distributing stakeholder information.
    D. Both contain escalation process.

    #3306
    admin
    Keymaster

    Correct answer is D.

    Escalation process is contained in the communications management plan only, not in the stakeholder management plan.