    Organizational process assets are updated as a result of both Manage Stakeholder Engagement process and Manage Communications process. In both the processes, process asset updates are same EXCEPT:

    A. Stakeholder notifications and feedbacks.
    B. Project reports and project presentations
    C. Project records
    D. The lessons learned are different

    #3157
    admin
    Keymaster

    Correct answer is D.

    OPAs updates are same in both processes, except lessons learned.