The communications management plan is different from the stakeholder engagement plan in that:
A. Communications management plan does not document identified interrelationships and potential overlap between stakeholders.
B. Communications management plan documents escalation process identifying time frames and
the management chains (names) for escalation of issues that cannot be resolved at a lower staff level.
C. Communications management plan documents glossary of common terminology.
D. Communications management plan documents communication constraints.