    The communications management plan is different from the stakeholder engagement plan in that:

    A. Communications management plan does not document identified interrelationships and potential overlap between stakeholders.
    B. Communications management plan documents escalation process identifying time frames and
    the management chains (names) for escalation of issues that cannot be resolved at a lower staff level.
    C. Communications management plan documents glossary of common terminology.
    D. Communications management plan documents communication constraints.

    #2523
    admin
    Keymaster

    Correct answer is A.

    Communications management plan does not document identified interrelationships and potential overlap between stakeholders. This item is mentioned in the stakeholder engagement plan.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Stakeholder Management Concepts: Project Stakeholder Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.