    You have been assigned the task of monitoring stakeholder engagements. For performing this process effectively, you require all the following inputs EXCEPT:

    a) Activity list
    b) Project management plan
    c) Issue log
    d) Work performance data

    #2484
    admin
    Keymaster

    Correct answer is A.

    Project Management Plan, Issue log, and Work performance data are required.