Managing stakeholder engagement generally results into project management plan update, mainly the
stakeholder engagement plan. Which of the statements does not describe need for updating stakeholder engagement plan?
A. When some communications may no longer be necessary
B. When an ineffective communication method may be replaced by another method
C. When existing risks are well managed
D. When a new communication requirement may be identified