    You have been tasked to develop stakeholder engagement plan. You have used expert judgment,
    meetings, and analytical techniques. You will include all the following information in this plan EXCEPT:

    A. Desired and current levels of the stakeholders
    B. Major requirements, main expectations, potential influence in the project, phase in the life cycle with the most interest.
    C. Information to be distributed to the stakeholders, including language, format, content, and level of detail.
    D. Scope and impact of change to stakeholders

    #2421
    admin
    Keymaster

    Correct answer is B.

    Other than what is mentioned in choice B, all other information is included in the stakeholder engagement plan. What is mentioned under choice B is included in the stakeholder register, not stakeholder management plan.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Stakeholder Management Concepts: Project Stakeholder Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.