    While identifying stakeholders, you need project charter. How does charter help you?

    A. Provides project approval requirements that help in identifying stakeholders.
    B. Provides information about internal and external parties related with the project and affected by the execution of the project, such as sponsor(s), customers, team members, groups and departments participating in the project, and other people and organizations affected by the project.
    C. Provides high-level requirements that helps identify stakeholders.
    D. Provides summary millstone schedule and budget that helps identify stakeholders.

    #2372
    admin
    Keymaster

    Correct answer is B.
    Charter provides all the information written in choices A, B, C, and D but the information that helps in stakeholder identification is choice B.

    Revise Stakeholder Management Concepts: Project Stakeholder Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.