    A Scrum team is working on a critical project. Since the project is of high importance, 2 new members joined the team to quickly complete the project. What effect would this situation has on the team velocity in the next iteration?

    a. Team velocity will be increased
    b. Team velocity will remain same
    c. Team velocity will be decreased
    d. Team should re-evaluate its velocity

    #11892
    admin
    Keymaster

    Correct answer is D.

    Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.

    Tips/Tricks/Cheatsheet to master Scrum Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    All Scrum Question & AnswersQuestion & Answers

    Revise Scrum ConceptsScrum Concepts

    Scrum UpdatesScrum Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.