  • #11915
    admin
    Keymaster

    You joined an organization which has recently adopted Scrum to execute projects. Senior Management is complaining that Team A is not performing efficiently as compared to Team B because their velocity is regularly lower than that of Team B. What would you do in such situation?

    a. Ask Team A to improve their velocity in the upcoming iterations
    b. Introduce reward structure which may increase motivation of Team A
    c. Move some members of Team B to Team A
    d. Inform Senior Management that velocity cannot be used as comparison metric between different teams

    #11918
    admin
    Keymaster

    Correct answer is D.

    Individual teams decide the size of story points based upon their own estimations, which cannot be compared across teams. Since velocity is the number of story points completed during an iteration, therefore, velocity too cannot be compared between two different teams.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master Scrum Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    All Scrum Question & AnswersQuestion & Answers

    Revise Scrum ConceptsScrum Concepts

    Scrum UpdatesScrum Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.