While completing work, a project team member tells you that a work package has been forgotten in the WBS. What is the BEST thing to do?
a) Wait for a change request to be processed.
b) Include it in the WBS
c) Include it only in the network diagram
d) Include it in the estimate, but not in the activity list.
Anything missed in the WBS should be added. However such changes should be evaluated in the Perform Integrated Change Control process. The change could then be added to a network diagram (choice C) and an estimate (choice D). Change orders (choice A) start after the project management plan is approved, not during planning.