Two months into a design project, the customer requested a modification to the product. The change was made without notifying the project manager. During the final testing phase, results were different than what was planned for. This scenario is BEST thought of as an example of which of the following?
a) Poor scope control
b) Poor adherence to the communications management plan
c) Poor development of the quality management plan
d) Poor definition of the test plan