Home › Forums › PMP Questions and Answers Discussion › Scope Management Question 22 This topic has 1 reply, 1 voice, and was last updated 5 years, 4 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts December 25, 2019 at 10:27 AM #3294 adminKeymaster A project is ending one of its phases, what should be done before moving on to the next phase? a) Team meeting b) Validate scope c) Management Meeting d) Scope management December 25, 2019 at 10:30 AM #3295 adminKeymaster The correct answer is B. The Validate Scope process is done at the end of each phase of the project. If it is not done, you risk delivering something in the next phase that is not acceptable to the customer. Pass PMP in the First Attempt : PMP Strategy Revise Scope Management Concepts: Project Scope Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In