    A project is ending one of its phases, what should be done before moving on to the next phase?

    a) Team meeting
    b) Validate scope
    c) Management Meeting
    d) Scope management

    #3295
    admin
    Keymaster

    The correct answer is B.

    The Validate Scope process is done at the end of each phase of the project. If it is not done, you risk delivering something in the next phase that is not acceptable to the customer.