  • #1796
    Gary
    Guest

    A project manager receives a deliverable from one of the team members to provide to the customer. While looking at the deliverable, the project manager notes that the document is smaller than what he expected and does not contain what he thought it should. The project manager should first:-
    a) Discuss it with the team member
    b) Contact the team member’s manager to get that person additional training
    c) Audit the development process
    d) Complete the verify scope process

    #1797
    Gary
    Guest

    The correct answer is D.

    Such a review compares the deliverable to the requirements. The project manager might have misunderstood and it would be best to check before talking to the team member.