A project manager is concerned about the amount of gold plating that has occurred on past projects. All of the following would NOT be of use in controlling gold plating EXCEPT?
a) Staffing management plan
b) Project charter
c) Work breakdown structure dictionary
d) Risk management plan
If you picked project charter (choice B) remember that the project charter is a high-level document. Because the WBS dictionary (choice C) is much more detailed, it would provide more help in controlling gold plating.