The correct answer is D.
A project manager cannot be responsible for the customer’s inspection process (choice A), only his own. Network diagram changes (choice B) will not affect the root cause of this problem. An apology (choice C) might be in order later, after the root cause is found. The best choice of those provided is to review the Validate Scope process (choice D) as that process deals with acceptance by stakeholders.