    A functional manager meets with the project manager’s boss to discuss a change to the acceptance criteria for a major deliverable. After the meeting, the boss calls the project manager into the office and tells him to make the change. What is the FIRST thing to do?

    a) Make the change as soon as possible
    b) Understand the change
    c) Supply the boss with the change form
    d) Evaluate the impact of change

    #2477
    admin
    Keymaster

    The correct answer is B.

    You need to first understand the change before you can evaluate it. In this instance, verbal communication is not likely to provide enough information to evaluate. Once you understand the change, you can work with the team to determine the impact and options.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Scope Management Concepts: Project Scope Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.