    The project manager wishes to use the Delphi technique to obtain expert opinion on some different technical issues. What should she be careful to do?
    a) Make sure the experts consulted are recognized for their input
    b) Compare information and work towards a single opinion
    c) Consult the stakeholders
    d) Meet together with the stakeholders to obtain the consensus.

    #2434
    admin
    Keymaster

    The correct answer is B.

    The rules of the Delphi technique are: keep the experts’ identities anonymous, do not bring the experts together in the same room, and build consensus.