Home › Forums › PMP Questions and Answers Discussion › Scope Management Question 11 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 12, 2019 at 5:06 PM #2361 adminKeymaster A WBS is BEST described as a tool for tracking? a) The schedule b) Resources c) Cost d) Scope October 12, 2019 at 5:08 PM #2362 adminKeymaster The correct answer is D. Work not in the WBS is outside the scope of the project. Revise Scope Management Concepts: Project Scope Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In