the preparation of the scope baseline can best be describes as involving?
a) The project team
b) All the stakeholders
c) Project expeditor
d) The functional managers
After the customer’s input, the performing organization’s project team is responsible for scope baseline preparation. The scope baseline includes the WBS, WBS dictionary, and project scope statement.