    Project Schedule Management Mockup Exam
    There are total 20 situational based questions in this mock-up exam based upon latest PMBOK version which is picked from database in the random order. Take mock-up exam several times and make sure all answers are correct to master the topic of Project Schedule Management.

    Based on the chart, what will be the effect on the project if activity C now takes 4 months?

    There is no change to the critical path
    Activity B is now on the critical path
    There will be new critical path
    The project will take longer