Home › Forums › PMP Questions and Answers Discussion › Schedule Management Question 9 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 16, 2019 at 12:23 PM #2389 adminKeymaster How is three point estimating related to risk? A It tells your how much assumption testing is required B It states whether the risk estimate is acceptable C It indicates the estimate degree of uncertainty D It indicates the risk variance October 16, 2019 at 12:26 PM #2390 adminKeymaster The correct answer is C. The wider the range between the optimistic and pessimistic estimates in a three-point estimate, the more uncertainty the estimator has. Pass PMP in the First Attempt : PMP Strategy Revise Schedule Management Concepts: Project Schedule Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In