Home Forums PMP Questions and Answers Discussion Schedule Management Question 8

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2363
    admin
    Keymaster

    During schedule development, which of the following BEST provides the basis for the MOST likely activity duration estimate?

    a) Labor productivity rates published by a professional association
    b) A consultant’s estimate of the overall labor man-hours required
    c) The initial estimate used to budget the project
    d) The schedule for the similar project at the same facility completed two years earlier

    #2365
    admin
    Keymaster

    The correct answer is D.

    This recent historical data (part of organizational process assets) provides the most unbiased and least subjective basis for the development of the initial project schedule.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.