    A project manager has reviewed his activity duration estimates from his team. Which of the following does he need in order to complete schedule development?

    A change requests
    B schedule change control system
    C recommended corrective actions
    D reserves

    #2255
    admin
    Keymaster

    The correct answer is D.

    Develop Schedule includes all work and uses all inputs needed to come up with a finalized, realistic schedule. One would need time reserves (choice D) in order to complete a schedule. All of the other items are parts of Control Schedule and occur after Develop Schedule.