    A problem occurs on an activity with the free float and the project manager has extended its duration. What is MOST likely to be affected?

    A Project duration
    B Resource schedules
    C Project scope management plan
    D The latest for the successor activity

    #2219
    admin
    Keymaster

    The correct answer is B.

    Since an activity with float will not affect the project duration as long as any delay is not greater than the float, choice A could not be best. Choice C cannot be best as this situation is not related to scope, just time. An activity with free float means it has time where it can be delayed without impacting the next activity. Therefore, choice D cannot be best. Any delay in when an activity is to be completed will most likely impact resources.

    Revise Schedule Management Concepts: Project Schedule Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.