Home › Forums › PMP Questions and Answers Discussion › Schedule Management Question 20 This topic has 1 reply, 1 voice, and was last updated 5 years, 3 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts January 6, 2020 at 3:51 AM #3314 adminKeymaster Which of the following techniques incorporates a form of risk assessment? a) Arrow diagramming method b) Network diagramming c) Critical path method d) 3 point estimation January 6, 2020 at 3:54 AM #3315 adminKeymaster The correct answer is D. Three-point estimation is based upon optimistic, realistic ahd pessimistic estimates, which takes into account the risk of not meeting your date. Pass PMP in the First Attempt : PMP Strategy Revise Schedule Management Concepts: Project Schedule Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In