    Which of the following does not need to be done if there is a major delay on a non-critical path activity?

    a) Investigate the delay
    b) Re-evaluate which path is critical
    c) Change the project schedule
    d) Review the float time for the activity

    #3178
    admin
    Keymaster

    The correct answer is C.

    You do not necessarily need to change the schedule, unless, of course, the delay is more than the activity’s float.