The correct answer is C.
Since the dependency is required, it could not be discretionary (choice A) and therefore must be mandatory. No mention is made that the dependency comes from a source outside the project, so external (choice B) is not correct. Scope dependency (choice D) is not a defined term. The key word in this question is “requires.” The question defines a mandatory dependency.
Pass PMP in the First Attempt : PMP Strategy
Revise Schedule Management Concepts: Project Schedule Management
Quiz:
20 Questions Challenge
50 Questions Challenge