    A dependency requiring that the design be completed before manufacturing can start is an example of?

    a) Discretionary dependency
    b) External dependency
    c) Mandatory dependency
    d) Scope dependency

    #2429
    admin
    Keymaster

    The correct answer is C.

    Since the dependency is required, it could not be discretionary (choice A) and therefore must be mandatory. No mention is made that the dependency comes from a source outside the project, so external (choice B) is not correct. Scope dependency (choice D) is not a defined term. The key word in this question is “requires.” The question defines a mandatory dependency.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Schedule Management Concepts: Project Schedule Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.