Home Forums PMP Questions and Answers Discussion Schedule Management Question 10

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2408
    admin
    Keymaster

    Lag means:

    a) The amount of time an activity can be delayed without delaying the
    project finish date
    b) The amount of time an activity can be delayed without delaying the early
    start date of its successor
    c) Waiting time
    d) The product of a forward and backward pass

    #2409
    admin
    Keymaster

    The correct answer is C.

    Total float and free float (choices A and B) are the time an activity can be delayed without impacting the entire project or the next activity. CPM (choice D) is a network analysis technique, not waiting time. Choice C is the correct answer.