Home Forums PMP Questions and Answers Discussion Risk Management Question 7

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2009
    admin
    Keymaster

    During the project, a team member tells you that a major risk identified by the team has occurred. However, it is not as serious as previously thought. What is the FIRST thing you should do?

    a) Increase the quality standard
    b) Present this finding to the project team and ask them to verify the team member’s finding
    c) Investigate changing the contingency plan
    d) Notify management

    #2010
    admin
    Keymaster

    The correct answer is C.

    Since the impact of the risk has changed, you need to ensure that the response is still appropriate for the situation.

    Revise Risk Management Concepts:
    Project Risk Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)